A fitted office can be a good choice when its layout, electrical installation and meeting rooms already support the way your team works. A bare-shell office gives you more freedom to design those elements together, provided the building can accommodate your requirements and the delivery programme is workable.
The difficult part is establishing how much of an existing fit-out is genuinely useful. Desks and glass partitions are easy to see during a viewing. Electrical capacity, internet installation requirements and speech privacy need closer investigation.
For businesses comparing offices in Hong Kong, the most useful question is: how much work will this particular unit need before our team can operate properly?
A fitted office has an existing interior installation, potentially including partitions, ceilings, lighting, flooring, joinery and cabling. Loose furniture may be included, separately negotiated or removed before handover. Ask for an inventory rather than assuming everything visible will remain.
A bare-shell office gives the incoming tenant responsibility for more of the interior works. The exact starting point varies. Confirm the landlord’s provision for floors, ceilings, electrical supply, air conditioning and fire services, including where each service terminates and the connections you must provide.
A partially fitted unit sits between these options. It can offer useful infrastructure without committing you to the previous occupier’s entire layout.
| Decision | Fitted Office | Bare-Shell Office |
| Layout | Potential to retain rooms and work areas that suit your brief | Greater freedom to plan within the building’s constraints |
| Electricity | Assess existing capacity, condition and circuit locations | Confirm incoming supply and define the tenant’s distribution works |
| Internet and IT | Check carrier service separately from inherited cabling and equipment | Plan carrier access, cabling, Wi-Fi and equipment locations together |
| Acoustic privacy | Assess existing rooms against your actual activities | Design room separation and acoustic treatment from the outset |
| Cost and timing | Depend on how much can be retained and what needs changing | Depend on the confirmed shell provision and full fit-out scope |
| Lease-end works | Confirm obligations for inherited as well as new installations | Confirm the required return condition before designing the fit-out |
Fitted, furnished and serviced describe different things. A serviced-office agreement may package space with connectivity, reception or other services. A conventional fitted-office lease does not automatically include those subscriptions or support arrangements.
Likewise, vacant possession, often described as 交吉, does not by itself mean bare shell. The premises can be vacant with the previous fit-out still in place. The written handover specification should settle what you will receive.
Before comparing quotations, write down your essential requirements: working headcount, room sizes, call patterns, confidentiality, equipment, operating hours and target move-in date.
Then review each shortlisted office with your fit-out and IT teams. Mark the plan in three categories:
Pay particular attention to changes that affect several systems. Moving a meeting room may also move lighting, ventilation, sprinklers, data outlets and AV equipment. An apparently small layout adjustment can therefore change the value of retaining the surrounding fit-out.
For every unresolved essential item, name the person who will obtain the answer and the evidence needed. A low initial quotation cannot compensate for an unconfirmed power upgrade or a connection date that misses your move.

A viewing shows the office as it stands on that day. Before committing to a fitted unit, ask the landlord or agent for a written handover schedule that identifies what will remain when you receive the premises. The schedule can include partitions, doors, lighting, flooring, pantry fittings, furniture, cabling and equipment, together with any items the outgoing tenant will remove.
Review the schedule against a marked-up floor plan and photographs. Where a desk cluster, access-control device or meeting-room screen is important to your plan, record whether it is included, who owns it and what condition is expected at handover. Also clarify who is responsible for removing unwanted items and making good the affected areas before your contractor starts.
Ask when your design team and relevant specialists can inspect the unit, what areas they can access and whether the landlord has drawings, approval records, equipment information or maintenance records. If the outgoing tenant is still using the premises, agree how inspections can take place around its operations and which checks must wait until the space is handed over.
Record important assumptions in the project brief and quotation. If a ceiling void or a service route cannot be inspected at the first visit, identify the follow-up check, the party responsible and how a discovery could affect the proposed scope and programme. Your project team can then revisit the decision once access is available.
Start with your workplace requirements and assess the existing fit-out against them. A meeting room may have the right dimensions and location, for example, but still need changes to its door, ventilation, power or video-conferencing setup. The decision to keep it should account for the complete scope needed to make it useful to your team.
For each major element, ask the design and construction team to consider its condition, suitability, ownership and the work needed to connect it with the new layout. Retaining a partition can be valuable when the surrounding services and circulation work with the new plan. If the room position has to change, compare the combined cost of adapting the partition, ceiling, lighting and services with the cost of an alternative layout.
Furniture, floor finishes and joinery can be assessed in the same way. Agree which items will be retained, repaired, relocated or removed, and include protection and any making-good work in the quotation. This gives the team a clearer scope and helps avoid pricing the same item differently across competing proposals.
Moving a glass partition may affect more than the visible wall. The project team may need to review ceiling finishes, light fittings, air supply and return paths, sprinklers or detectors, power and data outlets. A new enclosed room also needs to be considered alongside the building’s access, fire-safety and ventilation requirements.
Ask the relevant specialists to review the proposed room layout together before the alteration is priced and scheduled. Existing drawings and a site survey provide a starting point; any further opening-up or testing should be agreed with the parties responsible for the premises. The resulting scope can then be coordinated with building management and the applicable approval requirements.
A previous tenant’s successful occupation provides limited information about your requirements. Prepare an equipment list covering workstations, printers, pantry appliances, AV, network equipment and any dedicated cooling or specialist equipment.
Have a registered electrical contractor assess the proposed demand against the approved loading, supply arrangement and existing distribution. The assessment should also consider where power is needed. Sufficient incoming capacity can still require changes to circuits and outlet locations.
Request available drawings, circuit schedules and electrical records through the landlord or building management. Leave access to electrical enclosures and testing to authorised professionals.
Two records that may arise are WR1, the Work Completion Certificate, and WR2, the Periodic Test Certificate. They serve different purposes. EMSD’s guidance on electrical inspection and certification distinguishes certification of completed installation work, including affected parts after alterations, from periodic testing of specified installations.
Ask the contractor to establish which requirements apply and check what each record covers, when it was issued and whether subsequent changes have been made. A certificate for communal building services does not establish the condition of every installation inside your unit.
For bare-shell premises, confirm the supply and meter status, the connection boundary and the distribution work included in your fit-out. Starting with an empty interior does not itself increase the building’s available capacity.
If an upgrade is needed, establish feasibility, permissions and programme implications with the relevant utility and building parties. For example, CLP’s business change-of-load process calls for consultation with a registered electrical contractor and a rising-mains agreement from building management or the mains owner. Follow the supplier process applicable to the address.
An upgrade with a defined scope and supported programme can be costed. An upgrade whose feasibility remains unknown should remain an open condition of the property decision.
A building’s fibre connection is useful preliminary information. OFCA’s optical-fibre building register and labelling scheme identify buildings with optical-fibre access.
For your move, obtain confirmation from the intended carrier for the exact premises and service you need. Ask about the installation route, access to telecommunications risers, permissions, prerequisites and expected activation date. Record which dependencies remain outstanding.
Where business continuity requires a backup connection, ask the providers and your IT team to assess shared physical routes and other common dependencies. Two different provider names alone do not demonstrate independence.
Existing data outlets and a tidy rack can be valuable, but your IT team needs to know what connects to what. Request cable labels, patch-panel information, endpoint locations and available test records. Assess these against the planned network, wireless access points, video meetings and devices powered through network cabling.
Confirm ownership of racks and devices, and whether any licences or maintenance agreements are transferable. Have authorised IT staff securely recommission retained equipment; the previous tenant’s accounts and configuration should never be assumed suitable for the incoming business.
A bare-shell fit-out allows containment, outlets, access points, AV and IT-room power and cooling to be coordinated from the design stage. A fitted office can provide much of that foundation when the layout aligns. MJPM’s workplace technology integration service addresses these connections between the interior and its infrastructure.
Whichever option you choose, include service activation and testing of critical business applications in the occupation plan. For the subsequent move, the office IT relocation guide covers equipment, vendor coordination and commissioning in more detail.
A room for occasional video calls has a different brief from one used for confidential client discussions. Decide what conversations must remain private and which neighbouring spaces need protection from distraction.
It helps to distinguish two acoustic functions:

Carpets or acoustic wall panels can improve a room’s sound without resolving speech leakage through its door or ceiling void. The US General Services Administration’s workplace acoustic guidance and MJPM’s article explain why acoustic comfort depends on coordinated design. It is useful design guidance, rather than a Hong Kong statutory standard.
When assessing a fitted office, ask the appropriate specialist to consider the partitions, glazing, doors, seals, ceiling interfaces and service penetrations. Sound can also travel through shared ceiling spaces or ductwork.
Visit during representative building activity where possible. Note neighbouring conversations, plant noise and external noise. An informal listening check can identify concerns; it cannot certify confidentiality or replace specialist assessment where privacy is important. A product’s laboratory rating also needs to be considered alongside the completed room’s construction.
For a bare-shell office, agree the acoustic brief before fixing room positions and services. For a fitted office, establish whether the existing rooms can meet that brief through practical alterations. Changes to enclosures must be coordinated with ventilation, fire services and access requirements.
If the main shortfall is space for individual calls, phone booths and meeting pods may be worth assessing. Their performance, ventilation, placement and approval requirements still need review.
Use the same workplace brief for both options. A fitted-office estimate should include investigation, testing, repairs, selective removal, alterations and making good. A bare-shell estimate should start with the verified landlord provision and include the remaining works needed to deliver the office.
For both, identify professional and specialist input, IT and AV, furniture, building-required works, moving costs, overlapping occupation and appropriate contingency. Show refundable deposits separately from expenditure. Record exclusions explicitly so that a lower quotation is not simply a less complete one.
Compare the options over the same intended occupation period, including differences in rent, negotiated incentives and lease-end works.
Include operational requirements that may change the choice. Confirm central air-conditioning hours, after-hours availability and charges. Equipment needing cooling outside those hours requires a feasible arrangement. The same applies whether you retain an existing IT room or build a new one.
A fitted office can save time when substantial elements can be retained. That benefit reduces when extensive changes are needed or essential records and permissions are missing.
Check access dates, permitted work hours, landlord submissions, any applicable statutory requirements, nominated-contractor arrangements, procurement, utility work, carrier installation and final testing. Landlord or building-management consent and statutory compliance need separate consideration. Compare the supported date for business operations as well as the construction completion date.
For retained items, establish who owns them, who must maintain them, who pays for identified defects and what must happen at lease expiry.
For an office lease, establish repair and maintenance responsibilities in the agreed terms rather than assuming the landlord will repair inherited installations. The Rating and Valuation Department’s tenancy guidance on repair liabilities explains the limits of the repair-liability provisions in the Landlord and Tenant (Consolidation) Ordinance.
Ask your solicitor to review the actual lease, inventory, condition record and negotiated obligations. Taking over a fitted office does not automatically remove reinstatement exposure. Photographs are useful evidence, but the written agreement must establish which condition and obligations the parties have accepted.

Once the unit has been selected, a written programme helps the incoming tenant coordinate the property handover, design work, construction and technology setup. The order and duration depend on the premises and the agreed access arrangements, but the following steps provide a useful starting point:
Keep an open-items list throughout the process. For each item, record the decision needed, the person responsible and the date it affects. If a retained component needs additional work after inspection, the team can review its effect on the budget and move-in plan while the remaining work continues.
Consider a hypothetical 24-person consultancy choosing between two shortlisted offices. The fitted unit already has enough desks, two meeting rooms and a network rack. The bare-shell unit requires a new interior.
If the consultancy can retain the room locations, the electrical installation supports its equipment, cabling tests support reuse and the carrier confirms a workable connection programme, the fitted unit has a strong practical advantage. The team can direct its budget towards specific improvements.
Now change the brief. The firm needs several simultaneous confidential calls, the existing rooms cannot provide the required privacy without substantial reconstruction, and moving them triggers wider service changes. The fitted option now needs a larger adaptation budget. A bare-shell design deserves a fresh comparison, subject to confirmed building capacity and permissions.
The determining factor is the amount of suitable work retained after assessment. The number of existing desks tells only a small part of that story.
Ask for the relevant documents before the appointment, then use the visit to identify what needs follow-up:
A viewing helps identify questions. Technical verification and lease review provide different parts of the answer.
Bring the shortlisted floor plans, landlord handover schedules and workplace requirements to MJPM’s office fit-out project management team. A scoped feasibility and design discussion can help identify what is worth retaining, what needs changing and where specialist verification is required before you commit to the premises. Contact MJPM today.