MJPM works with businesses on office design and fit-out projects across Hong Kong. Some companies move into new premises, while others choose to reconfigure their existing workplace as their teams and operational needs change.
An occupied office restack brings those changes into a workplace that still needs to function. Staff need places to work, meetings need suitable rooms, and essential systems need to remain available while different areas are prepared for construction.
In this guide, we share the planning considerations that help businesses organise an office restack, from temporary seating and staff moves to building-services coordination and phased handovers. The aim is to give you a clearer picture of the decisions to make before work begins.
Office restacking is the reorganisation of people, workspaces and facilities within an existing office. It can involve moving teams between areas or floors, changing the layout of workstations, adding meeting rooms, updating finishes and coordinating changes to building services.
The scope depends on what the business wants to achieve. One company may need to bring several departments together on fewer floors. Another may want to replace a large workstation area with a mix of desks, meeting rooms and collaboration spaces.
Restacking can take place alongside an office renovation. In an occupied workplace, the project team plans the sequence around the areas that staff need to use and the areas that need to be handed over for construction. Teams may move into temporary space, completed areas or another part of the office as work progresses.
An office often begins to feel less suitable before a company decides it needs a major change. Meeting rooms may be difficult to book, teams that work closely together may be spread across different areas, or a floor designed for fixed desks may no longer match how staff use the office.
Restacking gives a business an opportunity to review the space it already occupies. It may be appropriate when the company wants to:
The starting point is a clear view of both the desired workplace and the activities that need to continue during the work. These requirements shape the final layout and the construction sequence.
Many office changes can be planned in stages, with staff working in one area while another is being reconfigured. The right approach depends on the scale of the work, the available floor area, the building’s services and the business’s operating requirements.
A project that mainly involves furniture changes and limited partition work may have a different sequence from one that includes extensive demolition or major electrical and air-conditioning alterations. Some phases may require staff to move away from the affected area, even when the wider office continues operating.
Before deciding on the programme, the business and project team should identify:
These answers allow the team to assess an occupied approach and decide how much work can be completed in each phase.

The first capacity question in an occupied office restack is how many people can work effectively while one part of the office is unavailable.
The final design may provide enough desks for the business, but the temporary arrangement needs its own plan. When a construction zone is closed, staff still need suitable places to work elsewhere. Those places may be existing desks, a rearranged part of the office or another temporary space agreed for the project.
A useful first check is to compare the expected number of people on site during a phase with the usable desks available outside the work zone.
| Illustrative phase-capacity check | Number |
|---|---|
| People expected on site on a busy day | 48 |
| Usable desks outside the construction area | 35 |
| Initial desk shortfall | 13 |
The team can then review options for the 13-person shortfall. These may include temporary workstations, an agreed attendance arrangement or a different phase boundary.
The calculation is a starting point. Some employees may need specialist equipment, access to confidential information or a seat close to their team. A desk is most useful when it supports the work the person needs to complete.
Swing space is a temporary working area used while another part of the office is being changed. It gives the project team room to move a group of staff out of a construction zone and prepare that zone for its next use.
Swing space can be an underused part of the existing office, a completed area made available early in the programme or another suitable temporary location. The choice depends on capacity, availability and the business’s requirements.
Before relying on a swing area, check that it has the essentials: appropriate desks and chairs, power, connectivity, access, storage and enough room for people to move comfortably. The temporary arrangement should also consider where staff can hold calls or meetings while their usual rooms are unavailable.
A phased restack divides the workplace into areas that can be handed to the construction team, worked on and returned to use in an agreed sequence. The number and size of phases depend on the floor plan, the work required and the space available for staff.
The following example illustrates a simple sequence:
| Phase | Workplace arrangement | Construction activity |
|---|---|---|
| Preparation | Confirm temporary desks, meeting spaces and staff move arrangements | Confirm work zones, access, deliveries and building requirements |
| Phase 1 | Team A moves into a suitable temporary area | Team A’s original zone is reconfigured |
| Phase 2 | Team B moves into the completed and released area | Team B’s original zone is reconfigured |
| Final phase | Remaining teams move to their agreed locations | Remaining work, checks and handover are completed |
Each move depends on the preceding area being ready. The project team therefore needs to coordinate the staff move plan with the construction programme, furniture delivery, technology setup and handover checks.
A floor plan showing the status of each area can make the sequence easier to understand. For each phase, it should be clear which spaces are occupied, which are being worked on, which routes remain available and where the next group will move.

Two restack plans can accommodate the same people while creating different experiences for staff. One useful point of comparison is how many times each team has to move.
A person-move means one person moving once from one working location to another. Someone who moves from their original desk to a temporary desk and then to a final desk has made two person-moves.
Consider an illustrative project involving 80 people:
| Plan | First 40 people | Second 40 people | Total person-moves |
|---|---|---|---|
| Plan A | Move twice: original desk → temporary desk → final desk | Move once: original desk → final desk | 120 |
| Plan B | Move twice | Move twice | 160 |
Both plans accommodate the same number of people, but Plan B involves 40 additional person-moves. Each move can involve packing, handling equipment, reconnecting workstations and helping staff settle into a new area.
The lowest number of moves is one consideration in the decision. Team relationships, privacy, access to equipment and the final layout may make another sequence more suitable. Counting moves helps the business see the trade-off and discuss it before the programme is fixed.
The best time for a construction activity depends on the business calendar as well as the contractor’s schedule.
A finance team may have month-end reporting deadlines. A client-facing department may need meeting rooms available for scheduled visits. An IT team may have a period when changes to the network are restricted. These commitments should be identified before staff moves and service interruptions are scheduled.
The project team can bring the two programmes together in one view:
| Illustrative week | Business activity | Construction activity |
|---|---|---|
| Week 1 | Finance team completes month-end work | Preparation takes place in another zone |
| Week 2 | Finance team moves to temporary desks | Work begins in the finance zone |
| Week 3 | Client meetings use an agreed alternative room | Partition and services work continues |
| Week 4 | Workstations and systems are checked | Completed zone is prepared for handover |
The actual sequence will depend on the project. The value of the exercise is that it shows where a construction activity and a business activity need the same space, service or time.
Regular coordination meetings also give the team an opportunity to update the plan. If a delivery, inspection or workstation setup changes, the affected staff move can be reviewed and communicated before it affects the next phase.
An occupied workplace has different demands from an empty floor. Staff, visitors and contractors may all need access during the same period, while deliveries and construction activities need to fit around the business’s normal operations.
A practical plan identifies the working area, the construction area and the routes between them. It should also explain how people enter the office, where materials are delivered, which facilities remain available and how changes will be communicated.
The project team should agree how construction zones will be separated from the working office and how staff and visitors will move around them. The arrangement depends on the layout and the activities taking place in each phase.
Deliveries, storage and waste removal should be considered at the same time. A corridor that looks wide enough on a drawing may also be used by staff, visitors and contractors throughout the day. Planning these movements early helps the team organise the space around its actual use.
Some work is easier to coordinate outside the busiest office hours. The team can identify activities likely to affect calls, meetings or nearby work areas and discuss suitable windows with the business and building management.
The permitted hours depend on the building and the scope of work. Agreeing them early gives the contractor a clearer basis for sequencing trades and gives the business time to adjust meeting schedules where necessary.
A new meeting room changes the office’s airflow as well as its floor plan. The partition and ventilation arrangements should therefore be reviewed together.
For example, a business may convert part of an open floor into two enclosed meeting rooms. The partition drawings show the new rooms, while the building-services review checks how supply and return air will work after the change.
The Hong Kong Labour Department’s ventilation guidance notes that changes to an office’s interior arrangement can affect ventilation and recommends reassessment when the way a space is used changes. During renovation, the project team should also plan suitable arrangements for the work area and adjacent occupied spaces.
MJPM’s office air-conditioning planning guide explains how room layouts, ventilation routes and operating hours influence these decisions.

A workstation move involves more than a desk and chair. Staff may depend on monitors, docking stations, phones, network connections, access systems, printers or specialised equipment to begin work in the new location.
The business should identify who is responsible for each part of the move. The fit-out contractor, furniture supplier and client’s IT provider may all have different roles, so those responsibilities should be clear before equipment is disconnected.
For each phase, the plan should cover:
The same principle applies to shared rooms and services. A completed meeting room should be checked against the business’s needs, including power, network access, display equipment and any booking or access arrangements.
A restack phase is ready for people when the space is ready for work: the construction area has been released and the systems needed by the incoming team are working.
A room may look complete while furniture, technology, cleaning or other agreed checks are still being finalised. A clear handover process gives the construction team and the business a shared understanding of what needs to happen before staff move in.
| Handover area | Question to confirm |
|---|---|
| Space | Is the area available for the incoming team, with any outstanding items recorded? |
| Workstations | Are desks, chairs, power and required equipment in place? |
| Technology | Have the relevant network, Wi-Fi, AV and access systems been checked? |
| Work environment | Have cleaning, ventilation and any agreed air-quality checks been completed? |
| People | Does the incoming team know where to go and whom to contact? |
| Approval | Who has agreed that the area can be used and the next move can proceed? |
The checks should be agreed around the project’s scope. Once an area has been handed back, the next phase can begin with greater clarity about where people will work and what the construction team can access.
The office restack programme needs to fit within the building’s operating arrangements. Requirements vary by property and by the proposed work, so early discussion with the landlord or building management team can help establish the practical constraints.
The project team may need to review:
Depending on the scope, the team may also need advice from the relevant building professionals on statutory requirements. The Buildings Department’s guidance on alterations and additions explains that different works can follow different approval or minor-works procedures.
These matters influence more than the construction start date. They can also affect when materials arrive, how staff moves are scheduled and how much time is needed between phases.
For businesses working in larger commercial buildings, MJPM’s IFC office relocation guide discusses how building requirements can shape fit-out planning and coordination.
The cost of an occupied restack includes the construction work and the temporary arrangements that allow the business to keep operating.
A project may need several handovers, temporary seating, protection, cleaning or work outside standard office hours. The business may also need to account for staff moves, IT reconnection, temporary storage or alternative meeting space.
| Construction programme | Workplace continuity |
|---|---|
| Partitions, finishes and building-services work | Temporary desks and meeting space |
| Deliveries, access and protection | Staff moves and equipment handling |
| After-hours work where required | IT reconnection and testing |
| Cleaning and phased handovers | Temporary storage or accommodation |
Some of these costs may sit with different suppliers or internal departments. Reviewing them together gives the business a clearer picture of the whole programme and helps it compare an occupied approach with other options.
The timeline is also shaped by the number and size of phases. A plan with limited temporary space may need smaller work zones and more handovers, while a larger available area may allow the team to work on a broader section at one time. The sequence should fit the project’s construction requirements and the business’s operating priorities.

MJPM’s Western Union Hong Kong project brings together open workstations, meeting spaces, glazed partitions and areas for staff to meet and collaborate.
The completed office includes spaces suited to different activities, from meeting rooms to pantry and breakout areas. Its layout illustrates how circulation, privacy and collaboration can be considered as part of the wider workplace design.
Before preparing a programme, bring the business, workplace and project teams together to discuss the following:
These questions give the project team a practical foundation for the design and programme. They also help the business understand how the workplace will function throughout the transition.
An office restack gives a business the opportunity to adapt its workplace around current needs while continuing to use the space it already occupies. Planning starts with the people who need to work there, the areas being changed and the order in which each space can be made available.
If you are considering an office renovation, consolidation or workplace reconfiguration in Hong Kong, contact MJPM to discuss your existing floor plan, operational priorities and the changes you want to make. Our team can help you review the design, construction and coordination decisions that will shape the project.